On Monday, May 16, work will begin in the Opwettenseweg to replace/adjust the sewers and storm water drainage to reduce future flooding. In order to cause as little disruption as possible, the work will be carried out in three phases:
Phase1: Monday May 16 to Friday June 10
Between Meijeraan and Berkenbos near the Witte Hondpad/Cockeveld.
One-way traffic will be established during this phase.
Phase2: Monday, June 20 through Monday, June 27
Intersection Laan door Panakkers - Opwettenseweg.
During this phase, Opwettenseweg will be closed to vehicular traffic at the work area.
Phase 3: Monday, June 27 until Friday, July 8
Corner of Vorsterdijk - Opwettenseweg.
During this phase the Opwettenseweg will also be closed to car traffic at the work site.
During the work, homes and businesses will remain accessible.