Traffic livability and accessibility measures
Increasing traffic is worsening the traffic livability and accessibility in Nuenen. We don't want that to happen. That is why the municipality, together with the Province of North Brabant, investigated this. A cohesive package of measures was then determined together with various parties. This package consists of 10 cohesive projects. The implementation of these projects will ensure that Nuenen's traffic livability and accessibility are maintained and in some areas even improved.
The package of measures was created through a participatory process in which various parties participated. Now begins the phase in which the projects are worked out, prepared and tendered. Here too, participation will take place with the parties involved. We are looking at which forms fit best here. Implementation of the first 3 projects is expected to start in 2027.
Elaboration of subprojects
The measures are divided into several subprojects. These include the following subprojects:
Opening of bus lanes Geldropsedijk - A270 to motorized traffic
We will open the existing bus lanes via the Geldropsedijk - A270 slip road to motorized traffic. This will improve Nuenen's accessibility and allow us to better distribute and control traffic in Nuenen. Naturally, safety is an important issue in the design of the new traffic situations. This also applies to the flow of public transport.
Narrowing Smits van Oyenlaan (south)
The consequence of the package of measures (in particular the opening of the A270 bus lanes) is that there will be slightly less traffic on Smits van Oyenlaan (between Klamperlaan traffic circle and the A270 junction). By narrowing the road here to a single lane, the road is better suited to the permitted speed of 50 km/h. A double lane in fact gives the impression that faster driving is allowed. So the narrowing will not change the legal speed, but the new design will increase traffic livability and safety. It also creates opportunities for a different (greener) use of the vacant space.
Construction of noise barrier on north side of A270 motorway
We are placing a noise barrier along the A270 (section between Smits van Oyenlaan and Geldropsedijk on the north side of the A270). We do this because it provides a great local improvement in the quality of life (noise). There are various possibilities for the noise barrier provision.
Snelfietsroute Gemert - Eindhoven- first part from municipal border Eindhoven to traffic circle 't Pluuke (Europalaan - Smits van Oyenlaan)
Gemert - Eindhoven express cycle route - second part & modifications Smits van Oyenlaan
- The express bike route part two goes from Pluuke traffic circle to N615 (Lieshoutseweg).
- The intersections on Smits van Oyen Avenue will be modified at a number of points, including traffic lights.
- In Gerwen there will be a village hub: a hub where different types of transportation come together.
Planning
Completed: Problem analysis, scenarios, sketch designs and decision - 2015 -2021
During the study we investigated the traffic livability and accessibility of the municipality of Nuenen. The study resulted in a realistic preferred alternative of (traffic) measures, supported by the province and municipality, with a sketch design and a rough cost estimate.
Completed: Administrative agreement and development of subprojects - 2023
The Province has reserved a contribution of €10 million for the Nuenen preferred alternative (VKA) Bundelroutes. The Regional Mobility Program stipulates that this amount will accrue to Nuenen for the realization of the VKA under the first condition that both parties enter into a management agreement (BOK).
Currently underway: Preparation of tender for subprojects 1 to 3 - second half 2024
The tender for the contractor for subprojects 1 to 3 is being prepared.
Still to be done: Form construction team, elaboration and design for subprojects 1 to 3 - first half 2025
In the first half of 2025, the construction team for subprojects 1, 2 and 3 will be formed. This is also when the elaboration and design of the projects will become more concrete.
Still to do: Participation subprojects 1 to 3 - mid-2025
Together with stakeholders, we will look at how best to implement subprojects 1 through 3.
Still to do: Finalize board agreement express bicycle route Gemert - Eindhoven - February 2025
By entering into a board agreement, the route and costs of the express bicycle route become final.
Still to do: Participation subproject express bicycle route section from from Pluuke traffic circle to N615 - mid 2025
Together with stakeholders, we will look at how best to set up subproject 4.
Still to be done: Start work on subprojects 1 to 3 - second half of 2026
Work on the first 3 subprojects is expected to take place starting in the second half of 2026.
Still to be done: Start work on subproject 4 - end of 2026
Work on subproject 4 is expected to take place beginning in late 2026.