Renovation The Monastery
Cultural center Het Klooster in Nuenen is home to many associations in the municipality of Nuenen. The multifunctional building is outdated and is therefore being renovated. It will be a functional and sustainable building: a social and cultural vibrant heart in the center of Nuenen that invites to stay. The associations that have their home in the Klooster, will soon have optimal facilities for their activities and work intensively together in Vereniging Het Klooster. Vereniging Het Klooster takes care of the management and exploitation of the village house, in which the social function comes first.
Update November 2, 2026: Key handover from the municipality to the association
On Monday, November 2, 2026, the key handover ceremony for the renovated Klooster took place: Alderman Marjan Vrijnsen-De Corte presented the key to Bram Soetendal, the president of the Ons Klooster Association. A special milestone for everyone involved! The key handover is not only a symbolic moment but also marks the beginning of a new era in which Ons Klooster will continue to develop into a vibrant place for Discovering, Meeting, and Experiencing.
Planning
Upcoming: Grand Opening of Ons Klooster - January 15, 16, and 17, 2027
A festive opening weekend for Ons Klooster in the form of a multi-day event.
Completed: Key handover - November 2, 2026
On November 2, 2026, the keys to the renovated monastery were handed over: Alderman Marjan Vrijnsen-De Corte presented the key to Bram Soetendal, the president of the “Ons Klooster” Association.
Completed: Opening of Ons Klooster - November 1, 2026
On November 1, 2026, Ons Klooster began operations—in other words, it opened to the public.
Completed: UserMigration to Ons Klooster—mid-October through November 1, 2026
The residents of Ons Klooster have moved into the renovated building in phases.
Completed: Handover of the renovated Klooster by the contractor - Completion date
On August 28, 2026, the contractor handed over the renovated monastery to the municipality, and the municipality accepted it.
Completed: Final interior design - April 2025
The final design of the layout of the new Convent is ready.
Completed: Start of renovation - January 2025
The actual renovation of The Monastery began in early January 2025.
Completed: Signing of the construction contract - December 2024
Thursday, December 19, 2024, the municipality and Royal Woudenberg signed the official contracting agreement for the renovation of The Monastery. After the official signing moment, they together unveiled the construction sign at Het Klooster.
Completed: Sale of Old Items - December 2024
A number of "old" items from The Monastery have been collected by interested residents.
Completed: Initial demolition work - mid-November 2024
Starting Nov. 11, the first (light) demolition work will take place in preparation for the actual renovation of The Monastery.
Completed: Open House at Het Klooster Temporalis - September 29, 2024
Sunday, September 29, 2024 was the open day of the Monastery Temporalis. A busy, pleasant, inspiring afternoon in which all associations and users could present themselves. In the aftermovie you can see a short atmospheric report.
Completed: Linden tree removed - September 2024
On September 5, 2024, the linden tree in the central square in The Monastery was removed. Indeed, as a village house, The Monastery will have an open and accessible character where the atmosphere of hospitality is palpable. This openness will also be visible in the interior and at the entrance. In preparation we will remove a number of items from The Monastery, such as the reception desk and the lime tree. In consultation with the owner we are looking for possibilities to incorporate parts of the lime tree in the new interior.
Completed: Relocation of users to Klooster Temporalis - April 2024
All users of The Monastery have moved into their temporary housing location: The Monastery Temporalis.
Completed: Tender process for contractor and interior architect completed - March 2024
After a successful tender process, the contractor and interior designer have been announced: Koninklijke Woudenberg is the structural contractor and LA | Architecten Ingenieurs will work on the interior design of The Monastery.
Completed: Pilot project launched - Summer 2023
In the summer of 2023, Marcia van den Wildenberg was hired as (independent) quartermaster. She brings all parties in The Klooster together and stimulates and facilitates them to translate the desired social impact into cooperation, projects and activities.
Key Handover: November 2, 2026
Photos: Interim Update on the Monastery, September 2026
Photos: Interim Update on the Monastery, April 2026
Photos interim update Monastery August 2025
Atmospheric images furnishing Monastery
Photos of demolition (November 2024)
Videos about the renovation of The Monastery
Principles & questions/answers about temporary housing
To manage the right expectations about the temporary housing, we have established some guiding principles/principles. We have also listed frequently asked questions from users and answers from the municipality. This information can be found on the Principles & Questions/Answers webpage.