Work on power grid in Nuenen east
Starting Monday, February 27, grid operator Enexis will perform work on the electricity grid in Nuenen east.
The aim is to work according to the schedule below:
- Week 09 (Feb. 27-March 3), construction of cables Van Homberghgaarde;
- Week 10 (March 6 to 10), construction of cables Anderegglaan;
- Week 11 (March 13 to 17, continued cable installation, Rauppl Avenue;
- Week 11, beginning week 11 (March 13 to 17), removal of landscaping Seitzenhof;
- Week 11, end of week 11 (March 13 to 17), installation of Seitzenhof grid station;
- Week 12, construction of cables Raupplaan;
- Week 12, Assembly work at Van Homberghgaarde power station;
- Week 13, continued construction of cables Raupplaan;
- Week 13, Remaining work (laying cables and assembly work)
- Week 14, Remaining work (laying cables and assembly work)
There will be some traffic disruption during this period. Enexis will communicate with local residents about the accessibility of their homes during the work. Raupplaan and Anderegglaan will be temporarily and briefly closed at some point; the contractor will indicate this with signs.
Do you have questions about the work?
If so, feel free to contact Richard Koenders. He can be reached Monday through Friday between 8 a.m. and 4 p.m. via telephone number 06 11 87 05 71 or via e-mail; Richard.Koenders@enexis.nl